Update for 7th Street West Reconstruction Project

Posted: August 15, 2023 | Updated: August 29, 2023

8-28-2023 Construction update for 7th St Reconstruction

Please follow the traffic control signage.

7th Street Project Detour
7th Street Project Detour

 

Upcoming schedule:

  • Backfill remaining portion of Highway 9 intersection
  • Planning to pave BOTH Hwy 9 patches starting Monday, 8/28. This will likely take about 3 days. This does NOT include cure time.
  • Sanitary sewer will be laid early next week to Stock Ave.
  • Once sanitary sewer is installed watermain will be laid from Hwy 9 to Stock Ave.